We finished the full showcase scope for a branded jewelry hall in Kuala Lumpur: 26 custom showcases designed, manufactured and installed within 60 days, with zero defects at the client’s final inspection.
How the 60 days were spent
Weeks 1–2 covered space measurement and 3D design sign-off. Production ran days 15–45 in our Guangzhou factory with weekly photo reports. Sea freight and customs took another week; installation and staff training closed the final week.
What made the schedule hold
- One design freeze: all 26 units approved in a single 3D review, no late changes
- Materials ordered at drawing sign-off, not at production start
- Weekly photo reports kept the client’s decisions fast
Result
The hall opened on the planned date. The client’s independent inspection listed zero defects across 26 units — glass, locks, lighting and finishes all passed first-time.
Planning a store opening with a fixed date? Tell us the date — we plan backwards from it. Free layout proposal within 48 hours.